Concrete estimating: how to price and bid concrete jobs
Concrete estimating is the work of turning a job into a price: measure the quantities, cost the materials, labor and equipment, add your share of company overhead, then add profit. Get one of those wrong and you either lose the bid or win a job that loses money. This guide walks through each step with the formulas written out, then carries a 24 × 30 ft driveway with tear-out from takeoff to a final bid. Every price in that example is a placeholder for your own numbers.
What concrete estimating covers
Concrete estimating means working out what a job will cost you to build and what you need to charge for it. Whether the concrete estimator is a full-time hire or the owner at the kitchen table at 9 pm, the order is the same:
- Takeoff: measure the quantities.
- Materials: price them at your suppliers’ current prices.
- Labor: convert quantities to crew-hours, then to dollars at a burdened rate.
- Equipment, disposal and permits, plus the small items that get forgotten.
- Overhead: add your company’s own overhead rate.
- Profit: set the price from a target margin.
- Proposal: write it, send it and follow it up.
Steps 1 to 4 add up to direct cost, the money the job itself consumes. Step 5 pays for the business that stands behind the job. Step 6 is what you keep. A lot of advice on how to estimate concrete jobs jumps from materials straight to “add 10 to 30%”, and that jump is where small contractors lose money.
Three words get used loosely. An estimate is your internal cost build-up. A bid or quote is the price and terms you send the customer. Keep them as two documents: the concrete estimate holds your labor rates and margins, and the quote holds scope, price and conditions.
Step 1: the concrete takeoff
Every concrete estimating job starts here. A concrete takeoff is the list of quantities you measure from the plans or the site before you price anything. For flatwork, pull these:
- Area in square feet: drives finishing, base, sealing and vapor barrier.
- Volume in cubic yards: drives the ready-mix order.
- Base in cubic yards, then tons at your quarry’s weight.
- Reinforcement: linear feet of rebar or the number of mesh sheets, plus chairs and tie wire.
- Forms in linear feet, noting edges that butt an existing slab and need isolation joint instead.
- Control joints in linear feet.
- Tear-out: area and thickness of whatever comes out.
The volume formula is the one every concrete calculator uses:
Cubic yards = length (ft) × width (ft) × thickness (in) ÷ 324
The 324 is 12 × 27: twelve inches to the foot and 27 cubic feet to the cubic yard. Add waste on top. Concrete Calculator defaults to 10% and rounds ready-mix up to the next quarter yard, because that is how plants sell it. The waste factor guide explains when to go higher, and how to calculate concrete has the formulas for footings, piers and steps.
Walk the site even when you have plans. Grade, truck access, the slope to the street and what sits under the old slab all change the price, and none of them show on a drawing. Ask the building department too: some towns set their own rules for the apron, such as a minimum thickness, specified steel and a form inspection before the pour, and those rules change the scope before you price it.
Concrete takeoff calculator or takeoff software?
A concrete takeoff calculator does the arithmetic for a shape you have already measured. Concrete takeoff software measures from digital plans: you trace areas and lines on the PDF and it totals them. For a residential driveway or patio measured with a tape, a calculator is enough, and the slab, driveway and yardage calculators on this site are free. Takeoff software earns its cost when you bid from plan sets: commercial work, multi-building projects, long footing schedules and plans that change with every addendum. A simple test: if you spend hours scaling drawings each week, software pays; if you measure on site, it probably doesn’t.
Step 2: price materials at your own supplier prices
Material prices vary by region, plant, mix and month, so this guide gives no national average for ready-mix; concrete estimating with someone else’s prices is guessing. Ask your suppliers for written prices and keep the date with each one:
- Ready-mix per cubic yard for each mix you place (strength, air, fiber, accelerator or retarder).
- Plant fees: fuel and environmental surcharges, after-hours or Saturday charges, winter heat.
- Minimum loads, short-load fees and how many yards one truck carries.
- Standby charges once unloading runs past the allowed time.
- Pump rates and minimums, if the truck can’t reach.
- Base stone per ton delivered, and its weight per cubic yard.
- Rebar per stick, mesh per sheet, chairs, tie wire, dowels.
- Isolation joint, curing compound, sealer, vapor barrier.
Prices drift. The Bureau of Labor Statistics producer price index for ready-mix concrete was 2.3% higher in August 2026 than in August 2025 (the 2026 figure is preliminary). That is one reason to put a validity period on every quote. The cost calculator compares bags against a ready-mix delivery, including delivery and short-load fees, at the prices you enter.
Step 3: labor from crew-hours, not square feet
Labor is the line in concrete estimating that decides whether a job makes money, and it’s the one most often guessed. Build it from your own crew-hours:
Labor-hours for a task = crew size × hours the task takes
Labor cost = total labor-hours × burdened hourly rate
The hours come from your own production rates: how much of each task your crew gets done per hour on a normal job. Record every job by task, quantity, crew size and hours. After ten or so jobs you’ll have rates you can trust, and you can adjust them for access, weather and finish. This guide doesn’t publish industry production rates, because the only one we found on the pages that rank for concrete estimating had no source. Fill in your own:
| Task | Unit | Your rate (units per crew-hour) | Your crew size | Adjust for |
|---|---|---|---|---|
| Saw-cut, break out and load old slab | sq ft | thickness, steel, access | ||
| Fine grade and compact base | sq ft | soil, haul distance | ||
| Set forms | lin ft | curves, grade changes | ||
| Set rebar or mesh | sq ft | spacing, dowels | ||
| Place, screed and finish | sq ft or cu yd | finish type, pump or chute | ||
| Saw-cut control joints | lin ft | usually a return trip | ||
| Strip forms, backfill, clean up | lin ft | |||
| Travel, loading and setup | per worker-day | distance to the job |
Your burdened labor rate
A bare wage isn’t what an hour costs you. Add the employer’s share of everything tied to payroll:
- Social Security: 6.2% employer share, on wages up to $184,500 in 2026 (IRS).
- Medicare: 1.45% employer share (IRS).
- Federal and state unemployment, at your rates.
- Workers’ compensation, at your policy’s rate.
- Paid leave, health insurance, retirement or union fringe, if you pay them.
Burdened rate = base wage × (1 + burden %)
For context, not as an input: in June 2026, BLS found that private construction employers spent $36.13 an hour worked on wages and $15.84 on benefits, so benefits were 30.5% of total compensation, or about 44 cents on every wage dollar. For cement masons and concrete finishers, the BLS May 2025 median wage was $27.41 an hour and the mean $28.87, with the 10th percentile at $18.84 and the 90th at $41.10. Your crew mix and local market decide your number.
Concrete labor cost per square foot
Concrete labor cost per square foot is your labor dollars divided by the slab area. In the worked bid below it comes to $2,696.80 ÷ 720 = $3.75 a square foot, for that job, that crew and those example wages. It moves with tear-out, thickness, finish, access and job size, because travel and setup don’t shrink on a small slab. Two of the pages that rank for this term publish labor ranges that barely overlap, and neither names a source. Your own number is the only one worth using.
Step 4: equipment, disposal and the costs estimators forget
Give owned equipment an internal daily or hourly rate that covers its payment, repairs and fuel, so the jobs that use it pay for it. Price rentals at the rental rate plus the trip to pick them up. Price disposal per load or per ton at your dump or recycler, and count the trucking time.
Then run the checklist. These are the lines that go missing from concrete estimating most often:
- Pump: boom or line, minimum hours, setup and washout.
- Short-load fee, a second truck, standby time, after-hours or Saturday charges.
- Tear-out and haul-off, including slabs thicker or more heavily reinforced than they look.
- Dump or recycling fees.
- Permits, inspections and the day lost waiting for one.
- Extra base for soft spots.
- Rebar chairs, tie wire and dowels into existing concrete.
- Vapor barrier under interior slabs.
- Isolation joint material where new meets old.
- Saw-cutting control joints, which is usually a return trip, plus blade wear.
- Curing compound, and sealer if it’s in the scope.
- Finish extras: steel trowel, stamping, color, release.
- Mobilization and demobilization, equipment transport.
- Weather: blankets, heat, accelerators, retarders, plastic for rain, lost days.
- Testing, if the spec calls for it.
- Sidewalk or street permits and traffic control.
- Cleanup, washout and repairing the lawn along the forms.
- Warranty callbacks.
Tear-out deserves its own warning. Old slabs turn out thicker than expected, carry mesh or rebar, or sit where a machine can’t reach, and removal prices for the same kind of job vary several-fold in forum threads. Check the thickness at an edge or with a test cut before you price it, and put the assumed thickness in the proposal.
Step 5: work out your overhead rate
Overhead is every cost of running the company that can’t be charged to one job, and it’s the step most concrete estimating advice skips. There are two standard ways to turn it into a rate:
Overhead rate (% of direct cost) = annual overhead ÷ annual direct job cost
Overhead per labor-hour = annual overhead ÷ annual billable field labor-hours
Use last year’s books, then adjust for what you expect this year. Here is an example with made-up numbers for a small flatwork company. They show the method; they are not benchmarks.
| Overhead item | Annual cost |
|---|---|
| Truck payments, fuel and vehicle insurance not charged to jobs | $24,000 |
| General liability and other insurance not charged on payroll | $18,000 |
| Office, phone and software | $6,000 |
| Owner’s salary for non-field time | $40,000 |
| Marketing | $8,000 |
| Accounting and legal | $5,000 |
| Yard or shop rent | $12,000 |
| Equipment depreciation and repairs not charged to jobs | $7,000 |
| Total annual overhead | $120,000 |
Say that company’s direct job costs last year were $600,000. Its overhead rate is $120,000 ÷ $600,000 = 20% of direct cost. Say it also had four field workers billing 1,600 hours each, or 6,400 labor-hours. Its overhead per labor-hour is $120,000 ÷ 6,400 = $18.75.
Method A is simple and works when your jobs are similar. Method B charges more overhead to jobs that tie the crew up longer, such as tear-outs and decorative work, which is closer to how overhead is really used up. Either beats a flat guess, and knowing this number is the heart of how to price concrete jobs that keep the business alive. One more point: pay yourself a field wage for field hours inside labor, put your office time in overhead, and treat profit as something separate from both.
Step 6: markup vs margin
Markup is profit as a percentage of cost. Margin is profit as a percentage of the selling price. They are not the same number, and every pricing page we reviewed for this guide that gave a profit percentage applied a markup and called it a margin.
Margin = markup ÷ (1 + markup)
Price = cost ÷ (1 − target margin)
Markup needed = target margin ÷ (1 − target margin)
| Markup on cost | Margin on price |
|---|---|
| 10% | 9.1% |
| 15% | 13.0% |
| 20% | 16.7% |
| 25% | 20.0% |
| 30% | 23.1% |
| 40% | 28.6% |
| 50% | 33.3% |
| Target margin | Divide cost by | Equivalent markup |
|---|---|---|
| 10% | 0.90 | 11.1% |
| 15% | 0.85 | 17.6% |
| 20% | 0.80 | 25.0% |
| 25% | 0.75 | 33.3% |
| 30% | 0.70 | 42.9% |
Here is what the mix-up costs. A job costs you $10,000 and you want a 20% margin. Add 20% and you quote $12,000; your profit is $2,000, which is 16.7% of the price. To keep 20% of the price you needed $10,000 ÷ 0.80 = $12,500. The confusion cost $500 on one job, and it repeats on every job you price that way.
Worked bid: a 24 × 30 ft driveway with tear-out
This concrete bid shows concrete estimating from start to finish on one job: replacing an old 4 in driveway with a new one. Every price, wage, rate, fee and production figure below is an example input. Replace each one with your own before you use the method.
Scope: break out and haul away the existing 24 × 30 ft slab; add 4 in of compacted base; form three sides (the fourth butts the garage slab, with an isolation joint); #4 rebar at 24 in on center each way (an example spec; follow the plans, the owner’s spec or local code); place 4 in of concrete with a broom finish and tooled edges; apply curing compound; saw-cut control joints; strip forms and backfill.
Takeoff
- Area: 24 × 30 = 720 sq ft
- Concrete: 720 × 4 ÷ 324 = 8.89 cu yd
- Add 10% waste: 8.89 × 1.10 = 9.78 cu yd
- Round up to the quarter yard: order 10 cu yd. Ask your plant whether that ships on one truck. Many full-size trucks carry 8 or 9 yards (see the bags vs ready-mix guide), which would mean a second truck and maybe a short-load fee.
- Base: 8.89 cu yd compacted, plus 15% for compaction = 10.22 cu yd loose. Say your quarry’s stone weighs 1.5 tons per cubic yard: 10.22 × 1.5 = 15.33 tons, so order 16 tons. The gravel calculator does this step.
- Rebar at 24 in each way: 13 bars × 30 ft = 390 lin ft, plus 16 bars × 24 ft = 384 lin ft, total 774 lin ft. Add 10% for laps and waste: 851.4 lin ft ÷ 20 ft sticks = 42.57, so 43 sticks.
- Forms: 30 + 30 + 24 = 84 lin ft.
- Control joints (example layout of panels about 12 × 10 ft): one 30 ft joint down the middle and two 24 ft joints across = 78 lin ft.
Labor
Say your crew’s average base wage is $26.00 an hour. Burden in this example: 6.2% Social Security + 1.45% Medicare + 3.0% unemployment (example) + 11.0% workers’ comp (example) + 8.0% benefits and paid leave (example) = 29.65%. Burdened rate: $26.00 × 1.2965 = $33.709, rounded to $33.71 an hour.
| Task | Quantity | Crew | Hours (example) | Labor-hours |
|---|---|---|---|---|
| Saw-cut, break out and load old slab | 720 sq ft | 3 | 6 | 18 |
| Fine grade and compact base | 720 sq ft | 3 | 4 | 12 |
| Set forms | 84 lin ft | 2 | 3 | 6 |
| Set rebar | 720 sq ft | 2 | 3 | 6 |
| Place and broom finish | 10 cu yd | 4 | 5 | 20 |
| Saw-cut control joints | 78 lin ft | 1 | 2 | 2 |
| Strip forms, backfill, clean up | 84 lin ft | 2 | 2 | 4 |
| Travel and setup | 12 worker-days | – | 1 each | 12 |
| Total | 80 |
Labor: 80 × $33.71 = $2,696.80.
Direct cost
| Line | Calculation | Amount |
|---|---|---|
| Ready-mix, say $165/cu yd | 10 × $165 | $1,650.00 |
| Plant fuel and environmental fees, say | lump sum | $60.00 |
| Base stone, say $32/ton delivered | 16 × $32 | $512.00 |
| #4 rebar, say $14 per 20 ft stick | 43 × $14 | $602.00 |
| Chairs and tie wire, say | lump sum | $55.00 |
| Form and stake wear, say | lump sum | $75.00 |
| Isolation joint, 24 lin ft, say | lump sum | $30.00 |
| Curing compound, say | lump sum | $40.00 |
| Materials subtotal | $3,024.00 | |
| Labor | 80 × $33.71 | $2,696.80 |
| Skid steer, breaker and trailer, say 1 day | $450.00 | |
| Plate compactor, say 1 day | $85.00 | |
| Walk-behind saw and blade wear, say | $150.00 | |
| Dump fees, say 4 loads at $60 | 4 × $60 | $240.00 |
| Permit, say | $100.00 | |
| Direct cost | $6,745.80 |
Overhead, margin and the final price
Using the example overhead rate of 20% of direct cost and an example target margin of 15%:
- Overhead: $6,745.80 × 0.20 = $1,349.16
- Cost including overhead: $6,745.80 + $1,349.16 = $8,094.96
- Price: $8,094.96 ÷ 0.85 = $9,523.48
- Check: profit is $9,523.48 − $8,094.96 = $1,428.52, which is 15.0% of the price and a 17.6% markup on cost.
With method B instead, overhead is 80 labor-hours × $18.75 = $1,500.00, cost is $8,245.80 and the price is $8,245.80 ÷ 0.85 = $9,700.94. The tear-out makes this a labor-heavy job, so the labor-hour method loads $150.84 more overhead onto it. You might round either figure for the proposal; just round up, not down.
Concrete pricing per square foot: a check, not a method
Concrete pricing per square foot is the bid price divided by the area. For the worked bid that’s $9,523.48 ÷ 720 = $13.23 a square foot. The tear-out lines alone (18 labor-hours, the skid steer and the dump fees) come to $1,296.78 of direct cost, or $1,830.75 once overhead and margin are applied: about $2.54 of every square foot.
That is why, in concrete estimating, a per-square-foot price is a check, not a pricing method. Mobilization, the truck minimum, the permit and setup cost about the same on a 200 sq ft pad as on a 1,000 sq ft drive, so small jobs cost more per foot. A 5 in slab takes 25% more concrete than a 4 in one. Tear-out, bad access, a pump, extra base and the finish each move the number. Price everything at one rate and you’ll underprice the small, thick, remote and tear-out jobs and overprice the big easy ones, so you win the wrong work.
A newly licensed contractor on the Fine Homebuilding forum once asked whether the per-square-foot driveway prices his mentors gave him would be profitable. The replies offered other people’s local rates, but nobody could answer the question, because a square-foot rate says nothing about your costs. Use the figure the other way round: compare it with your own past jobs of the same type, and if it’s far off, look for a mistake.
Concrete flatwork pricing vs foundations vs decorative work
Concrete flatwork pricing is driven by area: finishing labor, base prep, tear-out and a big crew on pour day. Forms are short and steel is light, so the variables are the ground, the access and the weather on the day you finish.
Foundations are driven by forming and steel. Wall forms, footing excavation, the rebar schedule on the plans, inspections before the pour and a pump on many sites all add time, and the concrete per square foot of building is far higher. Finishing is minimal. The footing calculator handles the volumes.
Decorative work (stamped, colored, exposed aggregate) is driven by finishing labor and risk. You need more hands at the right minute, release agents, color, sealing and often a sample panel. Callbacks over color variation or surface problems cost more, so carry a higher margin and spell out what the customer should expect.
A concrete estimate template you can copy
A concrete estimate template is the internal sheet where every quantity, price and rate lives, and for a small company it’s the backbone of concrete estimating. Build it once in a spreadsheet and copy it for every job:
| Column | What goes in it |
|---|---|
| Line item | Ready-mix, base, rebar, tear-out labor, pump… |
| Quantity | From the takeoff |
| Unit | cu yd, ton, lin ft, sq ft, labor-hour, day |
| Unit cost | Your supplier’s price or your burdened rate |
| Extension | Quantity × unit cost |
| Price source and date | Which supplier, which quote, what day |
Group the rows as takeoff, materials, labor by task, equipment, disposal and permits, then add direct cost, overhead, cost including overhead, target margin, price, and price per square foot as the final check. The source-and-date column is what lets you re-price an old estimate in five minutes when a supplier’s price letter arrives.
What the customer sees: a concrete quote template
A concrete quote template is the customer-facing version, and it never shows your labor rate or margin. Part of how to quote concrete jobs well is deciding what to show. Include:
- Your company details, license and insurance.
- The customer, the site, the date and how long the price is valid.
- A plain description of the work.
- The spec: thickness, mix strength, reinforcement, base, finish, joints and curing.
- The lump-sum price, and optional alternates with their own prices.
- Exclusions, and unit prices for unknowns.
- Schedule and payment terms.
- The weather, subgrade and cracking clauses, and how change orders work.
- A signature line.
Concrete estimating software: what to look for
Concrete estimating software comes in four broad types: spreadsheets you build yourself; takeoff software that measures from plans; estimating software with cost databases and assemblies; and field-service or CRM apps that include quote templates. Most “best software” lists are written by the vendors, so judge tools by these questions instead:
- Does it use your own cost data and production rates, not a canned database?
- Can you build assemblies, such as “4 in driveway, per sq ft”, that pull materials and labor together?
- Does it do on-screen takeoff from PDFs, if you bid from plans?
- Does it print a clean proposal with scope, exclusions and terms?
- Does it tie change orders to the original estimate?
- Does it track bids won and lost?
- Can you export your data if you leave?
- What does it cost per user as the team grows?
Run three of your past jobs through any trial and compare the result with what those jobs really cost. For concrete estimating on residential flatwork, plenty of contractors never need more than a good spreadsheet. Contractors have been asking for tools that hold their own prices rather than someone else’s database for a long time; if a tool can’t do that, the spreadsheet above will serve you better.
How to bid concrete jobs: writing the proposal
How to bid concrete jobs comes down to a clear, written proposal. Concrete bidding is won as much on clarity as on price, because a customer comparing three quotes can only compare what’s written down. In one Garage Journal thread, two similarly priced garage slab quotes used different reinforcement and neither said a word about the base, so the homeowner had no way to tell which was the better job.
Scope. Describe exactly what you’ll do and to what spec: thickness, mix strength, reinforcement, base depth and compaction, finish, joints and curing.
Exclusions. List what isn’t included: rock or buried debris, soft subgrade beyond the base allowance, an old slab thicker than stated, sealing, landscaping repair, irrigation or utility relocation, and permits if the owner pulls them.
Alternates and unit prices. Price options separately, such as rebar versus mesh, sealing, or a thicker slab or apron. Give unit prices for unknowns, such as extra base per ton installed or extra tear-out per square foot. Customers balk at an add-on that costs several times the concrete in it, as one Garage Journal thread about a thicker garage slab showed; pricing the option up front, with the second truck or extra forming it needs, heads that off.
Validity. State how long the price holds, because ready-mix prices move.
Payment terms. Deposit, progress payment and final payment, with dates or milestones. Some states limit how much a home improvement contractor can take as a deposit, so check with your state licensing board.
Weather clause. Say you’ll schedule the pour around the forecast, who decides to postpone, and that protection beyond the plan is extra. The American Society of Concrete Contractors has pointed out that contractors often take the blame when rain hits fresh flatwork, even where avoiding rain costs real time and money. Plastic on site and a written clause protect you better than an argument afterward.
Subgrade clause. Say the price assumes firm, unyielding subgrade, and what happens, at what unit price, if you find soft spots after tear-out.
Cracking language. Concrete cracks. Control joints are there to make cracks happen in straight lines where you want them. Say so, and say what you will and won’t warranty. Homeowners sometimes write specs demanding a crack guarantee; a concrete contractor on the Garage Journal forum called that a non-starter, and most will simply not bid it.
Change orders. Any change gets written down, priced and signed before the work is done.
Following up and tracking your win rate
Concrete estimating doesn’t end when the quote goes out. Follow up after you send it: a call or message within a few days, another after a week or two, then let it go. If you’re too busy for a job, say so quickly. Homeowner threads about contractors who never call back are full of people who would have accepted a polite no, and a fast no costs nothing.
Keep a bid log: date, customer, job type, price, price per square foot, won or lost, and why. Your win rate is jobs won ÷ bids sent. If you win almost everything, you’re probably too cheap. If you win almost nothing, check whether the problem is price, the jobs you chase or how you present the bid. The log also feeds your next concrete estimate, because it tells you which jobs you price well.
When to walk away from a bid
- The job is below your minimum: mobilization, a truck minimum and a crew day cost the same on a tiny pour, so set a minimum job price and stick to it.
- The customer wants a price by phone or from a photo, without a site visit.
- The scope is vague, or the spec demands guarantees no one can give, such as a crack-free slab.
- The schedule is unrealistic, or access is so bad you can’t price it with confidence.
- The work is outside your specialty.
- The payment history is bad, whether that’s a slow-paying general contractor or a customer who will only pay at the end.
- You can tell you’re the third quote for a decision already made.
Where Concrete Calculator’s free tools fit
Concrete Calculator handles the volume arithmetic so your time goes into pricing. Here is where each tool fits in a concrete estimating workflow:
- Takeoff: the slab, driveway, footing and yardage calculators.
- Base: the gravel calculator.
- Small pours and patches: the bag calculator and the bag yield guide.
- Bags or a truck: the cost calculator, with delivery and short-load fees at your own prices, and the bags vs ready-mix guide.
- Waste: the waste factor guide.
Concrete Calculator doesn’t price labor, overhead or margin. That part is the method above, and it’s the part that decides whether the job pays.
Frequently asked questions
What is concrete estimating?
Concrete estimating is working out what a concrete job will cost to build and what to charge for it: takeoff, materials, labor in crew-hours, equipment and disposal, overhead at your own rate, and profit as a margin on price.
How to bid concrete jobs
Visit the site, do the takeoff, price materials at your suppliers’ prices, convert tasks to labor-hours at a burdened rate, add equipment, disposal and permits, add your overhead rate, then divide by (1 − target margin). Send a written proposal with scope, exclusions, payment terms and clauses for weather, subgrade and change orders, and follow it up.
What is a concrete takeoff?
A concrete takeoff is the list of quantities measured from plans or the site: area, cubic yards, base tons, rebar or mesh, form length, control joints and tear-out. Cubic yards = length (ft) × width (ft) × thickness (in) ÷ 324, plus waste.
How to price concrete jobs
In concrete estimating, price from cost, not from a per-square-foot rate. Add direct costs, add overhead at your own rate (annual overhead ÷ annual direct cost), then set the price as cost ÷ (1 − target margin). A 20% margin means dividing by 0.80, which is a 25% markup.
Concrete pricing per square foot
Divide the bid price by the area. The worked 720 sq ft driveway with tear-out in this guide comes to $13.23 a square foot using example inputs. Use the figure to check a bid against your own past jobs, not to set the price.
Concrete labor cost per square foot
Divide your labor dollars by the area. In the worked example, 80 labor-hours at a $33.71 burdened rate is $2,696.80, or $3.75 a square foot. It rises on small jobs, thick slabs, tear-outs and difficult access.
What is the difference between markup and margin?
Markup is profit as a share of cost; margin is profit as a share of price. A 20% markup is a 16.7% margin. Margin = markup ÷ (1 + markup).
Do I need concrete estimating software?
Not for most small residential jobs measured on site; a well-built spreadsheet and free calculators cover them. Takeoff software pays when you bid from plan sets regularly. Look for tools that use your own costs, build assemblies, print proposals and track wins and losses.
What should a concrete estimate template include?
Internally: line item, quantity, unit, unit cost, extension and the price source and date, grouped into materials, labor, equipment and disposal, then overhead, margin and price. The customer’s quote shows scope, spec, price, alternates, exclusions, validity, payment terms and clauses, but never your rates or margin.
Sources
- US Bureau of Labor Statistics, Occupational Employment and Wage Statistics, May 2025, Cement Masons and Concrete Finishers (47-2051): median, mean and percentile hourly wages, retrieved through the BLS Public Data API 2026-10-11. bls.gov
- US Bureau of Labor Statistics, Employer Costs for Employee Compensation, Table 4, June 2026: construction industry wages and benefits per hour worked, checked 2026-10-11. bls.gov
- US Bureau of Labor Statistics, Producer Price Index, ready-mix concrete manufacturing (PCU327320327320), August 2025 and August 2026 (preliminary), retrieved through the BLS Public Data API 2026-10-11. data.bls.gov
- IRS, Topic no. 751, Social Security and Medicare withholding rates: employer rates and the 2026 wage base, page reviewed 2026-09-24, checked 2026-10-11. irs.gov
- Bruce Suprenant, “Rain, Rain, Stay Away from Fresh Concrete”, American Society of Concrete Contractors, The Voice, September 2017, checked 2026-10-11. ascconline.org
- Fine Homebuilding forum, “Driveway Pricing for Today’s Rookies”, 2004: per-square-foot pricing versus cost build-up, checked 2026-10-11. finehomebuilding.com
- Fine Homebuilding forum, “estimating with excel”, 2001: estimating with your own pricing data, checked 2026-10-11. finehomebuilding.com
- The Garage Journal forum, “Garage floor replacement quote”, 2018: comparing quotes with different scopes, checked 2026-10-11. garagejournal.com
- The Garage Journal forum, “Insane prices for additional concrete”, 2024: pricing a thicker slab as an add-on, checked 2026-10-11. garagejournal.com
- The Garage Journal forum, “Driveway specs”, 2012: crack guarantees in a homeowner’s spec, checked 2026-10-11. garagejournal.com
- The Garage Journal forum, “Concrete Driveway”, 2019: local driveway apron requirements, checked 2026-10-11. garagejournal.com
- The Garage Journal forum, “Busting out old concrete… why so difficult?”, 2014: tear-out methods and removal prices, checked 2026-10-11. garagejournal.com
- The Garage Journal forum, “Fed Up with lazy no show contractors”, 2017: follow-up and declining jobs, checked 2026-10-11. garagejournal.com