Volumetric concrete: how mix-on-site trucks work and what you pay

You need 2 cubic yards for a patio. The ready-mix plant will bring it, but 2 yards is far under a full truck, so a short-load fee goes on the bill. Then you spot a mix on site concrete truck that says you only pay for what’s poured.

That truck makes volumetric concrete. Here’s how it works, how to check what you’re billed for, and when it actually comes out cheaper.

Updated 2026-10-15. Compare quotes at your own prices.

What is volumetric concrete?

Volumetric concrete is batched by volume and mixed at your site, a little at a time, instead of at a plant. The truck carries sand, stone, cement and water in separate compartments. When the operator starts it, gates and meters feed each one into a mixing auger at the back, and fresh concrete comes out of the chute.

You’ll hear the same machine called a volumetric concrete mixer, a mobile concrete mixer (mobile mixer for short), an onsite concrete mixer or a volumetric truck. Contractors call the process on site concrete mixing. Different names, same truck.

There’s a standard for it, too. ASTM C685 covers concrete “made from materials continuously batched by volume” and mixed in a continuous mixer.

A regular ready-mix truck works the other way round. Its drum is loaded at the plant, so the concrete is already mixed on the drive to you. The clock starts before the truck leaves the yard.

How a volumetric concrete truck mixes on site: separate bins feed an auger at the back Sand Stone Cement Water Mixing auger Chute
Each material has its own compartment. Gates and meters feed them into the auger, which mixes and discharges in one pass.

How a volumetric concrete truck measures what you pay for

The explanations we read skip how the billing works. That’s what protects your money.

A drum truck bills you for the yards you ordered. A volumetric truck can bill for what it actually made, because it measures as it goes. We read the South Carolina Department of Transportation’s specification for these trucks, dated July 1, 2019, to see what a public agency demands. It requires:

  • a recording meter that measures the cement as it goes into the mix
  • a water meter that reads to the nearest 0.10 gallon
  • an onboard ticketing system that records all the material used and the total volume of concrete placed, with the mix and the start and end time of the pour
  • bins big enough to make at least 6 cubic yards

That ticket is your receipt for volumetric concrete delivery. Ask for it.

The same specification sets how close the proportions must be:

Proportioning tolerances, SCDOT Supplemental Specification 701.4.4.7 (2019)
MaterialAllowed error (SCDOT)
Cement and fly ash0 to +4% by mass
Sand (fine aggregate)±2% by mass
Stone (coarse aggregate)±2% by mass
Admixtures±3% by mass or volume
Water±1% by mass or volume

Cement can run a little over but never under. SCDOT also has each truck recalibrated at least once every 12 months, or any time the materials change, and wants a rating plate on the mixer from the Volumetric Mixer Manufacturers Bureau.

A truck that’s overdue for calibration still prints a tidy ticket. So the calibration date matters as much as the ticket does.

Volumetric vs a ready-mix drum truck vs bags

For a small job you have three ways to get concrete. They differ most on the things that change your bill.

Three ways to get concrete for a small job
Volumetric truckReady-mix drum truck80 lb bags
Where it’s mixedIn an auger at your site, as it poursAt the plant, kept turning in the drumBy you, in a mixer or a wheelbarrow
Time limitMaterials stay dry until the auger mixes themDischarge within 1½ hours under ASTM C94Your pace, one batch at a time
What you pay forVolume on the ticket, plus any trip or minimum chargeYards ordered, plus delivery, plus a short-load fee under the plant’s minimumThe bags, plus hours of mixing
Changing the mix mid-jobYes, the operator can switchNo, one mix per truckYes, if you change the bag
2 cubic yardsAsk for the ticketed priceUnder most plants’ minimum, so expect a fee90 bags

That drum clock is real. ASTM C94, as quoted by the American Society of Concrete Contractors, says discharge has to be finished within 1½ hours of the mixing water meeting the cement and aggregates. The buyer can waive it only if the concrete can still be placed without adding water.

Highway work tightens it in the heat. The FHWA’s bridge-deck checklist allows 90 minutes or 300 drum revolutions below 80°F, and 60 minutes at 80°F or above.

Short load concrete is where this matters most. Plants set their own minimums, and our guide to how many yards of concrete fit in a truck lists the thresholds we found.

Is volumetric concrete cheaper?

Sometimes. It turns mostly on how far your job sits under the ready-mix plant’s minimum.

Prices are local, so we won’t hand you a national figure. Anyone who does is guessing about your town. Get two quotes for the same job instead and compare them like this:

  1. Drum truck: price per yard times yards ordered, plus the delivery fee, plus the short-load fee if you’re under the minimum.
  2. Volumetric truck: price per yard times the yards on the ticket, plus any trip or minimum charge.
  3. Bags: 2 cubic yards is 90 bags of 80 lb mix at about 0.60 cubic feet each, plus your own labor.

Concrete Calculator has a cost tool with fields for the short-load fee and delivery, so the drum quote and a bag price sit side by side in a minute. Put the volumetric quote through the same per-yard line.

Watch how the volumetric quote is built. A contractor on Long Island described local yards charging a mobilization fee that covers the first yard, then a lower rate for each yard after. With several ready-mix plants close by, he found a short load cheaper for 2 or 3 yards. So the drum truck can win even on small jobs, if a plant is near.

Volumetric tends to win when you’re far under the minimum, or when you don’t know your exact volume. If you’re billed by the ticket, over-ordering costs nothing, and less leftover concrete goes to waste.

When it’s a good choice, and when it isn’t

Mix on site concrete makes the most sense when:

  • you don’t know the exact volume, say a footing trench that might run long
  • the job needs more than one mix, like a slab plus some post holes
  • the pour will be slow or broken into sections
  • you’re ordering well under a plant’s short-load threshold

Skip it for one big continuous pour on a job site close to a plant. A full drum load avoids the fee and unloads fast.

Check your paperwork, too. South Carolina’s DOT allows volumetric mixers for non-structural concrete, and for structural concrete only case by case, with approval. On one Washington job an inspector refused anything but a ticket from the local ready-mix plant, even for a single small thrust block. If an engineer or inspector has set a mix for your project, ask them first.

Is volumetric concrete good? It can be. The standard exists and the tolerances are tight. But the quality rides on a calibrated truck and an operator who knows the mix.

One known weak spot: the auger sometimes mixes for only a few minutes, so a mix can stiffen fast, which admixture maker Fritz-Pak calls false set. Ask the operator how they prevent it.

What to ask before you book a mobile concrete truck

A few questions on the phone save most of the trouble:

  • When was this truck last calibrated? SCDOT asks for at least every 12 months, and a VMMB rating plate on the mixer.
  • Will I get a printed ticket showing the volume placed?
  • Do you bill by the ticket or by what I order? Is there a mobilization, minimum or trip charge?
  • What strength in psi can you make, and does your mix meet ASTM C685?
  • How fast does it pour for a job my size, and how do you handle a mix that stiffens early?
  • Where does it wash out, and can it reach my forms?

Write the answers down. If the quote is verbal, ask for it by text or email.

Work out your yardage first

Every quote above starts with a volume. Measure length, width and thickness, run them through the cubic yards calculator or the slab calculator, and keep the 10% waste allowance. Concrete Calculator rounds the order up to the next quarter yard, the same steps plants sell in.

Then get both quotes in writing and put them through the cost calculator. That’s the decision made.

Questions people ask before booking one

Is volumetric concrete as strong as ready-mix?

It can be. Volumetric concrete is covered by ASTM C685 and ready-mix by ASTM C94, and both are made to a mix design. Ask for the strength in psi and the truck’s last calibration date.

Do you really only pay for what’s poured?

That’s the idea, and the ticket records the volume placed. Ask whether they bill by the ticket and whether there’s a mobilization or trip charge, because that’s where a small job’s cost hides.

What size jobs suit a volumetric concrete truck?

Small or uncertain ones, and jobs that need more than one mix. SCDOT’s specification has the bins hold enough for at least 6 cubic yards, so one truck covers a typical patio or footing pour.

Is there a time limit with mix on site concrete?

Not the way there is with a drum. The materials stay dry and separate until the auger mixes them, so nothing starts setting until it’s coming out of the chute. Once it’s placed, you finish it on the same clock as any concrete.

Sources

  1. South Carolina Department of Transportation, Supplemental Specification 701.4.4.7, Volumetric Concrete Mixers, July 1, 2019: compartments, cement and water meters, onboard ticket, capacity, tolerances, calibration, VMMB rating plates and permitted use. scdot.org
  2. ASTM International, C685/C685M-25a, Standard Specification for Concrete Made by Volumetric Batching and Continuous Mixing: scope. astm.org
  3. American Society of Concrete Contractors, Position Statement #32, Concrete Discharge Time Requirements: ASTM C94 discharge time and purchaser waiver. ascconline.org
  4. Federal Highway Administration, Bridge Deck Construction 4 (generic review checklist), updated June 27, 2017: discharge time and drum revolutions. fhwa.dot.gov
  5. QUIKRETE Concrete Mix Data Sheet, Product No. 1101, revised October 2022: yield per 80 lb bag. quikrete.com
  6. Heavy Equipment Forums, “Volumetric concrete” thread, March 2018: contractor accounts of inspector requirements and volumetric pricing structure. heavyequipmentforums.com
  7. Fritz-Pak, “Why Does False-Setting Concrete Affect Volumetric Trucks?”, August 12, 2025 (admixture manufacturer). fritzpak.com